Elevator Construction - Summer, 2002
While the Ballard Masonic Center is "dark" this summer (2002), an elevator is being installed to serve the groups which meet there. It will be located just inside the front door on Market Street, and will service three floors: the basement, ground floor, and the Lodge floor.
Work is first starting in the basement, where a "service pit" must be installed to allow access to the bottom of the elevator. The first pictures where taken on June 20th after WB Richard Castleberry and WB Barry Knowles had broken and removed the concrete floor, and dug out the pit area. In the process, unforeseen sewer pipes had to be moved, and trouble with the water table had to be addressed.
Click the pictures for more detail.